METHOD STATEMENT FOR EXTERNAL PAINTING WORKS BY JOTUN PAINTS

15th May 2019 - METHOD OF STATEMENTS
METHOD STATEMENT  FOR  EXTERNAL PAINTING WORKS BY JOTUN PAINTS

REVISION DESCRIPTION SHEET

Rev. Paragraph Revision Description
00 First submission for Engineer’s review and approval.
     
     
     
     
     
     
     
     
     
     

Table of Contents

1.         SCOPE.. 4

2.         PURPOSE.. 4

3.         DEFINITIONS. 4

4.         REFERENCES. 4

5.         RESPONSIBILITIES. 6

6.         EQUIPMENTS & MATERIALS. 7

7.         HSE.. 8

8.         PROCEDURE.. 8

9.         TERMITE TREATMENT. 16

10.       QUALITY ASSURANCE.. 16

11.       APPENDICES. 17

1.         SCOPE

      This Method Statement outlined the following items;

2.         PURPOSE

The purpose of this Work Method Statement for External painting Works is to outline and describe in detail the procedure such as surface preparation, applying sequent putties / coats and all other related activity. Inform all concerned supervisor including workers the value and importance of this activity prior to implementation. This activity should be performed with strict compliance and implementation of Safety Requirements & Procedure and project specifications to complete the work of external painting.

3.         DEFINITIONS

MOI               Ministry of Interior (Employer)

GIJV              Consultant: Gesbau Italconsult Joint Venture

BEC                Beijing Emirates International Construction Co. (Contractor)

IFC                 Issued For Construction

QD                 Quality Department

QCP               Quality Control Plan

ITP                 Inspection and Test Plan

JHA                Job Hazard Analysis

STA                Safety Task Assignments

QCI                Quality Control Inspector

MSDS            Material Safety Data Sheet

TDS               Technical Data Sheet

PPE                Personal Protective Equipment

4.         REFERENCES

      Specification and Documents listed below are referred to;

5.         RESPONSIBILITIES

Project manager is responsible for maintaining the safety and progress of the work. He shall ensure that he has the latest drawings of the project and have updated information from the Engineer regarding project.

The Construction Manager is responsible for the arrangement of the work.

The HSE Manager is responsible for reviewing this procedure method statement, ensuring that the method statement, JSA and STA are carried out at the required time by the Safety Officer. Ensuring that all operatives are briefed on the method statement and operatives have signed to confirm receipt of briefing

The Safety Officer is responsible for the following:

Site Engineer and Survey team is to insure that external painting work is carried out as per required specifications and Method of Statement. To insure that all parties required any kind of inspection or test are suitably informed as to the delivery program. Insure that the notification time to QC is sufficient to meet notification time to Engineer.

Site Foreman team must work together to ensure that all activities regarding external paint shall be carried out properly. Preparation of area and necessary requirements for the execution of this method of statement must be carried out carefully to ensure safety and on-time delivery of work.

Shall be responsible for the Painting Application Works.

6.         EQUIPMENT & MATERIALS

The following tools and equipment shall be used during external painting Works.

Note: The type and quantities of equipment are subject to change to suit the site requirements.

7.         HSE

The foregoing procedure for the External painting works will serve as a guide or reference to the SE and QCE along the course of their work to achieve an acceptable quality of workmanship, and at the same time to control materials utilization and attaining the optimum results with less time and effort as:

  1. Application

Apply paint in accordance with the manufacturer’s directions. Use applicators and techniques best suited for the type of material being applied as following JOTUN’s Procedure.

The QCE shall invite the engineer to witness the foregoing procedure as per the submitted IRs (Inspection Requests).

An IR will be offered to the Engineer after surface preparation is completed. Once the Engineer approves that the surface is ready for the first coat application, an IR for first coat application will be offered for inspection. Likewise, an IR will always be offered to the Engineer for inspection and acceptance on the subsequent applications for the second, third, fourth and final coat activities.

Frequency of inspection requests shall be as per the approved ITP.

12    QUALITY ASSURANCE:

  1.  
DESCRIPTION OF WORK IN-CHARGE
The QA/QC Manager will monitor and ensure that this Method Statement shall be observed so that smooth Work Flow will be attained. Furthermore, the QA/QC Team shall ensure that each individual elements of the work shall be completed substantially in compliance with the approved plans and project specifications to meet client’s expectation. The following activities shall be observed: Single Source Responsibility: Provide primers and other undercoat paint produced by same manufacturer as finish coats. Use only thinners approved by paint manufacturer, and use only within recommended limits.Coordination of Work: Review other Sections of these Specifications in which prime paints are to be provided to ensure compatibility of total coatings system for various substrates. Upon request from other trades, furnish information       or characteristics of finish materials provided for use, to ensure compatible prime coats are used.Material Quality: Provide manufacturer’s best quality trade sale paint material of various coating types specified. Paint material containers not displaying manufacturer’s product identification will not be acceptable.   QA/QC Manager       QCE, SA  

13.        APPENCICES:

13.1                                                                             Inspection and Test Plan.

13.2                                                                             Checklists.

METHOD STATEMENT BRIEFING RECORD

(External Painting Works)

STONE SHIELD

BY

JOTUN PAINTS

Briefing delivered by:

Position: QA/QC Manager

Date: 08.06.2016

We (the undersigned) have read and understood the attached method statement and will comply with the specified requirements and control measures. If the work activity changes or deviates from that originally envisaged, we will seek further advice and request an amended method statement.

APPENDIX – 11.1

INSPECTION AND TEST PLAN

 

APPENDIX – 11.2

CHECKLISTS