Menu

METHOD STATEMENT FOR FAÇADE STONE MECHANICAL CLADDING

15th May 2019 - METHOD OF STATEMENTS
METHOD STATEMENT  FOR  FAÇADE STONE MECHANICAL CLADDING

REVISION DESCRIPTION SHEET

Rev. Paragraph Revision Description
00 First submission for Engineer’s review and approval.
     
     
     
     
     
     
     
     
     
     

Table of Contents

1……. SCOPE.. 4

2……. PURPOSE.. 4

3……. DEFINITIONS. 4

4……. REFERENCES.. 4

5……. RESPONSIBILITIES.. 5

6……. EQUIPMENTS & MATERIALS.. 6

7……. HSE.. 6

8……. PROCEDURE.. 7

9……. FREQUENCY OF INSPECTION.. 9

10…. QUALITY ASSURANCE.. 9

11….. APPENDICES. 9

1.         SCOPE

      This Method Statement outlined the following items;

2.         PURPOSE

The purpose of this Work Method Statement for Façade stone mechanical cladding works is to outline and describe in detail the procedure such as setting and lay-out plan on actual location, collecting accessories, fixing hanging systems and all other related activity. Inform all concerned supervisor including workers the value and importance of this activity prior to implementation. This activity should be performed with strict compliance and implementation of Safety Requirements & Procedure and project specifications to complete the work.

3.         DEFINITIONS

MOI               Ministry of Interior (Employer)

GIJV              Consultant: Gesbau Italconsult Joint Venture

BEC                Beijing Emirates International Construction Co. (Contractor)

IFC                 Issued For Construction

QD                 Quality Department

QCP               Quality Control Plan

ITP                 Inspection and Test Plan

JHA                Job Hazard Analysis

STA                Safety Task Assignments

QCI                Quality Control Inspector

MSDS            Material Safety Data Sheet

TDS               Technical Data Sheet

PPE                  Personal Protective Equipment

4.         REFERENCES

      Specification and Documents listed below are referred to;

5.         RESPONSIBILITIES

Project manager is responsible for maintaining the safety and progress of the work. He shall ensure that he has the latest drawings of the project and have updated information from the Engineer regarding project.

The Construction Manager is responsible for the arrangement of the work.

The HSE Manager is responsible for reviewing this procedure method statement, ensuring that the method statement, JSA and STA are carried out at the required time by the Safety Officer. Ensuring that all operations are briefed on the method statement and signed to confirm receipt of briefing

The Safety Officer is responsible for the following:

   Site Engineer has to insure that all the façade stone cladding work are carried out as per required specifications and Method of Statement. To insure that all parties required any kind of inspection or test are suitably informed as to the delivery program. Insure that the notification time to QC is sufficient to meet notification time to Engineer.

Site Surveyor is responsible to allocate all façade stone cladding levels as indicated in all arch. Drawings under instruction of SE, IR has to be issued and approved.

Site Foreman team must work together to ensure that all activities regarding façade stone cladding works shall be carried out properly. Preparation of area and necessary requirements for this method of statement must be carried out carefully to ensure safety and on-time delivery of work.

Shall be responsible for the façade stone cladding application works.

6.         EQUIPMENT & MATERIALS

Materials Tools & Equipments
All Systems are such  as but not limited to the following:     Approved Granite or marble with type, color, finish and dimensions as per drawings, manufacturer approval.Grouts and fillers as per manufacturer instructions with color of Engineer’s approval.Accessories with Anchors Stainless Steel: Type 304, for anchors, dowels and clamps in direct contact with stone.Hot-Dip Galvanized Steel: For anchor bolts, nuts and washers not in direct contact with stone which shall be provided by a specialized firm. Cleaning tools Drill machine Cutting tool Leveling tools Finishing tools   Set of minor tools

Materials are subjected to GIJV’s approval and installed in site as per manufacturer recommendation

7.         HSE

The foregoing procedure for the façade stone cladding Works will serve as a guide or reference to the SE and QCI along the course of their work to achieve an acceptable quality of workmanship, and at the same time to control materials utilization and attaining the optimum results with less time and effort as:

The QCE shall invite the engineer to witness the foregoing procedure as per the submitted IRs (Inspection Requests).

An IR will be offered to the Engineer after levels allocation is completed. Once the Engineer approves that the starting of system fixation for granite installation, an IR for will be offered for inspection. Likewise, an IR will always be offered to the Engineer for inspection and acceptance on the subsequent final activities.

Frequency of inspection requests shall be as per the approved ITP.

10    QUALITY ASSURANCE:

  1.  
DESCRIPTION OF WORK IN-CHARGE
The QA/QC Manager will monitor and ensure that this Method Statement shall be observed so that smooth Work Flow will be attained. Furthermore, the QA/QC Team shall ensure that each individual elements of the work shall be completed substantially in compliance with the approved plans and project specifications to meet client’s expectation. The following activities shall be observed: Single Source Responsibility: Provide materials same manufacturersCoordination of Work: Review other Sections of these Specifications in which materials are to be provided to ensure compatibility of complete stone mechanical cladding system for various sequences. Upon request from other trades, furnish information or characteristics of materials provided for use, to ensure compatible components are used.Material Quality: Provide manufacturer’s best quality trade sale granite/ Marble material of various stone types specified. Accessories material containers not displaying manufacturer’s product identification will not be acceptable.   QA/QC Manager       QCE, SA  

11 APPENCICES:

11.1                                                                       Inspection and Test Plan.

11.2                                                                       Checklists.

11.3                                                                       Risk Assessment.

METHOD STATEMENT BRIEFING RECORD

(Stone mechanical cladding system)

Briefing delivered by:

Position: QA/QC Manager

Date: 25.05.2016

We (the undersigned) have read and understood the attached method statement and will comply with the specified requirements and control measures. If the work activity changes or deviates from that originally envisaged, we will seek further advice and request an amended method statement.

APPENDIX – 11.1

INSPECTION AND TEST PLAN

APPENDIX – 11.2

CHECKLISTS

APPENDIX – 11.3

RISK ASSESSMENT

Leave a Reply

Your email address will not be published. Required fields are marked *